Palomino Center Roof Repairs

Palomino Center roof is being repaired due to minor leaks.

Timeline:

Friday, July 12- Sunday, July 14           Receive materials and stage

Monday, July 15- Saturday, July 20     Begin installation on Section “A & B”.

Sunday, July 21- Saturday, July 26       Begin installation on Section “C & D”

Sunday, July 28- Saturday, August 3    Begin Installation on Section “E”, and start details, and cleanup on ALL sections

palomino-center-roof-2.jpg

Staging Area and Flagged off Areas:

Palomino Center Roof